Forum Discussion
Saaam1165
Jan 15, 2025Copper Contributor
Project for web - calendar
Hi, on Project for web i've different plan with same/different resource. I've created a "calendar resource" with its own work calendar, then i'm using this resource as calendar template for all my ...
- Jan 16, 2025
Hello Saaam1165 ,
That is correct, the resource is a single entity that can be added to multiple plans. The resource can only have 1 calendar.
Paul
Saaam1165
Jan 16, 2025Copper Contributor
Hi Paul,
i need that because our resources could work in more department so i need to schedule that on a calendar for each department plan.
But from my understanding i could only manage the resource calendard (in common with all plans) or the plan calendar (common for all resources in plan), is that right? No other ways?
Thanks!
Paul_Mather
Jan 16, 2025MVP
Hello Saaam1165 ,
That is correct, the resource is a single entity that can be added to multiple plans. The resource can only have 1 calendar.
Paul