Forum Discussion

Pet3Art's avatar
Pet3Art
Copper Contributor
Jul 20, 2021

Project for the Web Power BI Template, exclude template projects from reporting

This must have been asked and answered but I just can't find it...

The great "Project for the Web Power BI Template" includes by default all the project form the portfolio. We have some labeled "Master: xxx" and flagged as favorites so the PMs can use them as templates, and do not have to start from scratch.

Is there a ways to simply exclude these from the reporting in the "Project for the Web Power BI Template" ?

thanx all

Petr  

2 Replies

  • Hello Pet3Art ,

    Yes you can do. Open the report in Power BI desktop and click Transform data. Expand the queries on the left hand side, in the Project for the web > Staging Queries folder click "Projects Staging". Scroll along the table until you see the column "msdyn_subject" and click the arrow on the column heading then click Text Filters. Select "Does not begin with" and enter "Master:" and click OK. You should now see the Master projects removed from the data set. Click Close & Apply.

    Hope that helps

    Paul

    • plankton365's avatar
      plankton365
      Copper Contributor

      Thanks! Paul_Mather 

      I tried this today and it worked for portfolio dashboard but the rest of the template tabs have the data from the excluded projects. Any ideas why this is happening?