Project for the Web Power BI Template, exclude template projects from reporting
This must have been asked and answered but I just can't find it... The great "Project for the Web Power BI Template" includes by default all the project form the portfolio. We have some labeled "Mas...
Paul_Mather
Jul 21, 2021MVP
Hello Pet3Art ,
Yes you can do. Open the report in Power BI desktop and click Transform data. Expand the queries on the left hand side, in the Project for the web > Staging Queries folder click "Projects Staging". Scroll along the table until you see the column "msdyn_subject" and click the arrow on the column heading then click Text Filters. Select "Does not begin with" and enter "Master:" and click OK. You should now see the Master projects removed from the data set. Click Close & Apply.
Hope that helps
Paul
- plankton365Aug 24, 2022Copper Contributor
Thanks! Paul_Mather
I tried this today and it worked for portfolio dashboard but the rest of the template tabs have the data from the excluded projects. Any ideas why this is happening?