Forum Discussion

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    Steve_Hayes 

    Linking structures in Project (master/subprojects, resources pool/sharer files, external dependencies) are all very fragile and do not work in some instances. I don't know how MS Teams is structured but if it is similar to SharePoint or OneDrive, then your cross-project linking is either going to be sporadic or not work at all. You might want to read this similar post on the Project section of the Answers forum:

    https://answers.microsoft.com/en-us/msoffice/forum/all/ms-project-linking-subprojects-error/60165fb3-5937-4ee8-8799-ccc5d1ed80dd

     

    I suggest you move the files to your local drive, link up as desired and then save and upload the resultant file back to the Teams folder, or copy the Timeline to another app for upload.

    John

    • Steve_Hayes's avatar
      Steve_Hayes
      Copper Contributor
      Hi- many thanks for your reply. I will start the migration process from SharePoint to shared network!

      Regards
      • John-project's avatar
        John-project
        Silver Contributor
        You're welcome and thanks for the feedback.
        Just for reference, hosting a linked [Project] structure on anything other than your local drive is rolling the dice for corruption. Links in Project are fragile and can become easily corrupted.

        John