Project 2019 not linking External Predecessors correctly for some tasks but correctly for other task
Hi I'm experiencing errors linking to some external tasks but not to all tasks. Attachment has detailed screenshots of error Any assistance would be greatly appreciated!! Regards
Steve_Hayes
Nov 09, 2021Copper Contributor
Hi- many thanks for your reply. I will start the migration process from SharePoint to shared network!
Regards
Regards
John-project
Nov 10, 2021Silver Contributor
You're welcome and thanks for the feedback.
Just for reference, hosting a linked [Project] structure on anything other than your local drive is rolling the dice for corruption. Links in Project are fragile and can become easily corrupted.
John
Just for reference, hosting a linked [Project] structure on anything other than your local drive is rolling the dice for corruption. Links in Project are fragile and can become easily corrupted.
John