Forum Discussion
Steve_Hayes
Nov 08, 2021Copper Contributor
Project 2019 not linking External Predecessors correctly for some tasks but correctly for other task
Hi I'm experiencing errors linking to some external tasks but not to all tasks. Attachment has detailed screenshots of error Any assistance would be greatly appreciated!! Regards
John-project
Nov 09, 2021Silver Contributor
Linking structures in Project (master/subprojects, resources pool/sharer files, external dependencies) are all very fragile and do not work in some instances. I don't know how MS Teams is structured but if it is similar to SharePoint or OneDrive, then your cross-project linking is either going to be sporadic or not work at all. You might want to read this similar post on the Project section of the Answers forum:
I suggest you move the files to your local drive, link up as desired and then save and upload the resultant file back to the Teams folder, or copy the Timeline to another app for upload.
John
Steve_Hayes
Nov 09, 2021Copper Contributor
Hi- many thanks for your reply. I will start the migration process from SharePoint to shared network!
Regards
Regards
- John-projectNov 10, 2021Silver ContributorYou're welcome and thanks for the feedback.
Just for reference, hosting a linked [Project] structure on anything other than your local drive is rolling the dice for corruption. Links in Project are fragile and can become easily corrupted.
John