Overallocation and scheduling conflicts - Project Desktop

Hello, I have an issue with marked overallocation in some tasks with predecessors (3 activities unfold in the same day of 8 hours, one of them continuing in the following days) for some resources which do not seem to over overallocated in that period, the allocation sum in the corresponding period being <=100

Yet, there appear some scheduling conflict errors, reported for the last tasks in the flow (following the predecessors - successors activities), these last tasks being scheduled much later than the ones with overallocation

The message in Inspector is 'Resources assigned in nonworking time' - for the 2 resources with marked overallocation. Yet, the days with overallocation are working days.

Could the problem appear from the scheduling conflicts? Actually I do not see clearly the scheduling conflicts as well

And then how are these overallocations computed?

Could you please help me solve this issue?

If necessary, I can attach the Project file

Thank you very much!

  • John-project's avatar
    John-project
    Mar 28, 2023

    Alina_Andreica 

    Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.

    John

  • Alina --

    I think we need to see your project, if you are willing to share it. I simply cannot visualize what is going on with your project. Let us know. Thanks!
      • John-project's avatar
        John-project
        Silver Contributor

        Alina_Andreica 

        Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.