Forum Discussion
Overallocation and scheduling conflicts - Project Desktop
- Mar 28, 2023
Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.
John
Dale_HowardMVP Hello Dale, and thank you for your answer
Actually, it's one of my students' project, but I cannot see why resources Coordinator and Beneficiary are overallocated in the subtasks of T5
Thank you very much!
Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.
John
- Alina_AndreicaMar 28, 2023Copper ContributorThank you very much John, I haven't noticed that!
Indeed, I've set the availability to 100% and it works now!
Thank you again!- John-projectMar 28, 2023Silver ContributorAlina_Andreica,
You're welcome and thanks for the feedback. Sometimes an inadvertent click of the mouse can send you into a lot of head scratching later on.
John- Alina_AndreicaMar 28, 2023Copper Contributor
John-project Yes, ideed! Especially since the click was not mine
Thank you again, your reply was very helpful!