Overallocation and scheduling conflicts - Project Desktop

Hello, I have an issue with marked overallocation in some tasks with predecessors (3 activities unfold in the same day of 8 hours, one of them continuing in the following days) for some resources whi...
  • John-project's avatar
    John-project
    Mar 28, 2023

    Alina_Andreica 

    Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.

    John