Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.
John
I think we need to see your project, if you are willing to share it. I simply cannot visualize what is going on with your project. Let us know. Thanks!
- Alina_AndreicaMar 28, 2023Copper Contributor
Dale_HowardMVP Hello Dale, and thank you for your answer
Actually, it's one of my students' project, but I cannot see why resources Coordinator and Beneficiary are overallocated in the subtasks of T5
Thank you very much!
- John-projectMar 28, 2023Silver Contributor
Not to upstage any analysis Dale might provide, but I took a quick look at your file. On the Resource Usage view, take a look at Work Availability in the Details column for the Coordinator resource. It shows as zero. If you then look at Resource Availability on the Resource Information you will see it is set to 0%. The same is true for the Beneficiary resource. Fix those and you should be good to go.
John
- Alina_AndreicaMar 28, 2023Copper ContributorThank you very much John, I haven't noticed that!
Indeed, I've set the availability to 100% and it works now!
Thank you again!