Forum Discussion
In Task Usage or Resource Usage, is it possible to summarize hours by group through Custom Fields?
For example, in Project Professional's Task Usage or Resource Usage, if I use a Custom Field such as Text1 to group tasks and resources, can I then display summarized hours by group in the left-side timesheet column and in the Detail Styles on the right-side time scale?
2 Replies
- Ignacio_MartinSteel Contributor
Hi Jasonzhengz,
insert the custom field column into the appropriate view, then click the black triangle in the column header (AutoFilter) and select "Group by this field."
Note: The "Text1" custom field in the Task Usage view, for example, is a task field; it is different from the "Text1" field in the Resource Usage view, which is a resource field.
I hope this helps.
- John-projectSilver Contributor
Jasonzhengzx0204,
Unfortunately, no. Custom fields are not timescaled. There might be some tricks you could use with manual entry into extra baseline fields, but I haven't really tried that to see if it's even feasible.
John