In Task Usage or Resource Usage, is it possible to summarize hours by group through Custom Fields?
For example, in Project Professional's Task Usage or Resource Usage, if I use a Custom Field such as Text1 to group tasks and resources, can I then display summarized hours by group in the left-side ...
Ignacio_Martin
Oct 05, 2026Steel Contributor
Hi Jasonzhengz,
insert the custom field column into the appropriate view, then click the black triangle in the column header (AutoFilter) and select "Group by this field."
Note: The "Text1" custom field in the Task Usage view, for example, is a task field; it is different from the "Text1" field in the Resource Usage view, which is a resource field.
I hope this helps.