Forum Discussion
Jasonzhengzx0204
Aug 15, 2026Copper Contributor
In Task Usage or Resource Usage, is it possible to summarize hours by group through Custom Fields?
For example, in Project Professional's Task Usage or Resource Usage, if I use a Custom Field such as Text1 to group tasks and resources, can I then display summarized hours by group in the left-side ...
John-project
Aug 17, 2026Silver Contributor
Jasonzhengzx0204,
Unfortunately, no. Custom fields are not timescaled. There might be some tricks you could use with manual entry into extra baseline fields, but I haven't really tried that to see if it's even feasible.
John