In Task Usage or Resource Usage, is it possible to summarize hours by group through Custom Fields?
For example, in Project Professional's Task Usage or Resource Usage, if I use a Custom Field such as Text1 to group tasks and resources, can I then display summarized hours by group in the left-side timesheet column and in the Detail Styles on the right-side time scale?
1 Reply
- John-projectSilver Contributor
Jasonzhengzx0204,
Unfortunately, no. Custom fields are not timescaled. There might be some tricks you could use with manual entry into extra baseline fields, but I haven't really tried that to see if it's even feasible.
John