Forum Discussion

xpsychic's avatar
xpsychic
Copper Contributor
Aug 10, 2022

Dynamic Duration in MS Project where start and finnish date of a task both bases on predecessors

Hello

 

Is it possible to base both start and finish date of a task on e.g. the start or finish date of two other tasks?

This will cause the duration for the affected/questioned task to become dynamic.

 

lets say I have

 

task 1: Send message to Techcom

Task 2: Confirm answer from Techcom received

Task 3: Evaluate answer from Techcom

 

I would set up the start/finish (and then automaticly duration) for task 3, so that it would not start before task 1 is done (1fs) and then finish date for task 3 so that it would be once task two is finish + 5 days (2fs + 5 days). 

Is this even possible or is it just the startdate of a task you can base on a predecessor?

 

Thanks

Br

X

 

    • xpsychic's avatar
      xpsychic
      Copper Contributor

      Dale_HowardMVP 

       

      Worked out fine. Thanks

      Do you know if there is somehow you can show the "logic" behind this on the tasks where you have choosed to use this "function"?

      Sort of same way as the predecessors does?

       

      Thanks again

      • John-project's avatar
        John-project
        Silver Contributor

        xpsychic 

        There is a partial visual queue for hammock tasks and that is a small triangle in the lower right corner of the hammock task. Double-clicking on fields with this indicator will take you to the source of the link.

         

        Unfortunately there is no such indicator in the linked fields of the source tasks.

         

        Hope this helps.

         

        John

Resources