Dynamic Duration in MS Project where start and finnish date of a task both bases on predecessors
Hello Is it possible to base both start and finish date of a task on e.g. the start or finish date of two other tasks? This will cause the duration for the affected/questioned task to become dyn...
Aug 10, 2022
xpsychic --
Yes, this is possible using what is known as a Hammock Task. Refer to the following blog post for the steps needed to create a Hammock Task:
https://www.projility.com/create-a-hammock-task/
Hope this helps.
Yes, this is possible using what is known as a Hammock Task. Refer to the following blog post for the steps needed to create a Hammock Task:
https://www.projility.com/create-a-hammock-task/
Hope this helps.