Dynamic Duration in MS Project where start and finnish date of a task both bases on predecessors
Hello Is it possible to base both start and finish date of a task on e.g. the start or finish date of two other tasks? This will cause the duration for the affected/questioned task to become dyn...
xpsychic
Aug 10, 2022Copper Contributor
Worked out fine. Thanks
Do you know if there is somehow you can show the "logic" behind this on the tasks where you have choosed to use this "function"?
Sort of same way as the predecessors does?
Thanks again
John-project
Aug 12, 2022Silver Contributor
There is a partial visual queue for hammock tasks and that is a small triangle in the lower right corner of the hammock task. Double-clicking on fields with this indicator will take you to the source of the link.
Unfortunately there is no such indicator in the linked fields of the source tasks.
Hope this helps.
John