Forum Discussion

23dV2095's avatar
23dV2095
Copper Contributor
Dec 19, 2023
Solved

Custom field calculation not working perfectly

Microsoft Project Standard 2016

Custom text field

Formula:

IIf([% Complete]<> 100 And [Scheduled Finish]<Now(),"Late",IIf([% Complete]<>100 And [Scheduled Finish]-Now()<15,"Due:,""))

 

If % complete not equal to 100% and scheduled finish is in the past, then display "Late"

If % complete not equal to 100% and scheduled finish is less than 15 days in the future, then display "Due"

 

Formula works fine. However, if I open the file it does not recalculate (as the definition of Now() is likely different). Changing the duration of any incomplete tax causes recalculation properly.

 

Is there a way to make this recalculation occur whenever the file is opened?

 

 

 

 

 

 

 

 

 

 

 

  • Hi Dan.

    Try [Current Date] field instead of Now()

    The formula would look like this:

    IIf([% Complete]<>100 And [Scheduled Finish]<[Current Date],"Late",IIf([% Complete]<>100 And [Scheduled Finish]-[Current Date]<15,"Due",""))

    Ignacio

5 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    23dV2095,
    Try using the Current Date field instead of Now.

    John
    • 23dV2095's avatar
      23dV2095
      Copper Contributor
      Thanks, I've changed it, will check tomorrow to see if it works.
  • Hi Dan.

    Try [Current Date] field instead of Now()

    The formula would look like this:

    IIf([% Complete]<>100 And [Scheduled Finish]<[Current Date],"Late",IIf([% Complete]<>100 And [Scheduled Finish]-[Current Date]<15,"Due",""))

    Ignacio