Custom field calculation not working perfectly
Microsoft Project Standard 2016 Custom text field Formula: IIf([% Complete]<> 100 And [Scheduled Finish]<Now(),"Late",IIf([% Complete]<>100 And [Scheduled Finish]-Now()<15,"Due:,"")) If % comp...
- Dec 19, 2023Hi Dan.
Try [Current Date] field instead of Now()
The formula would look like this:
IIf([% Complete]<>100 And [Scheduled Finish]<[Current Date],"Late",IIf([% Complete]<>100 And [Scheduled Finish]-[Current Date]<15,"Due",""))
Ignacio
Ignacio_Martin
Dec 19, 2023Steel Contributor
Hi Dan.
Try [Current Date] field instead of Now()
The formula would look like this:
IIf([% Complete]<>100 And [Scheduled Finish]<[Current Date],"Late",IIf([% Complete]<>100 And [Scheduled Finish]-[Current Date]<15,"Due",""))
Ignacio
Try [Current Date] field instead of Now()
The formula would look like this:
IIf([% Complete]<>100 And [Scheduled Finish]<[Current Date],"Late",IIf([% Complete]<>100 And [Scheduled Finish]-[Current Date]<15,"Due",""))
Ignacio