Forum Discussion
23dV2095
Dec 19, 2023Copper Contributor
Custom field calculation not working perfectly
Microsoft Project Standard 2016 Custom text field Formula: IIf([% Complete]<> 100 And [Scheduled Finish]<Now(),"Late",IIf([% Complete]<>100 And [Scheduled Finish]-Now()<15,"Due:,"")) If % comp...
- Dec 19, 2023Hi Dan.
Try [Current Date] field instead of Now()
The formula would look like this:
IIf([% Complete]<>100 And [Scheduled Finish]<[Current Date],"Late",IIf([% Complete]<>100 And [Scheduled Finish]-[Current Date]<15,"Due",""))
Ignacio
John-project
Dec 19, 2023Silver Contributor
23dV2095,
Try using the Current Date field instead of Now.
John
Try using the Current Date field instead of Now.
John
23dV2095
Dec 19, 2023Copper Contributor
Thanks, I've changed it, will check tomorrow to see if it works.