Consecutive task
Hi,
I have a task that I want to be performed consecutively, so if there’s a holiday in the middle, the software will postpone the beginning of the task to the next day when it can be performed continuously.
How do I do this?
3 Replies
- eyalk2300 --
Which tool are you using? Microsoft Project desktop or Project for the Web? Let us know and we will try to help you.- eyalk2300Copper ContributorMicrosoft Project desktop
- eyalk2300 --
You will need to edit the Standard calendar so that includes the holdiay you mentioned. Refer to the following YouTube videos on how to edit the Standard calendar:
https://youtu.be/GrR8v1Y4RN0
https://youtu.be/UOCuJdC9Oqc
Hope this helps.