Consecutive task
Hi, I have a task that I want to be performed consecutively, so if there’s a holiday in the middle, the software will postpone the beginning of the task to the next day when it can be performed cont...
Sep 17, 2024
eyalk2300 --
Which tool are you using? Microsoft Project desktop or Project for the Web? Let us know and we will try to help you.
Which tool are you using? Microsoft Project desktop or Project for the Web? Let us know and we will try to help you.
- eyalk2300Sep 17, 2024Copper ContributorMicrosoft Project desktop
- Sep 17, 2024eyalk2300 --
You will need to edit the Standard calendar so that includes the holdiay you mentioned. Refer to the following YouTube videos on how to edit the Standard calendar:
https://youtu.be/GrR8v1Y4RN0
https://youtu.be/UOCuJdC9Oqc
Hope this helps.