Consecutive task
Hi, I have a task that I want to be performed consecutively, so if there’s a holiday in the middle, the software will postpone the beginning of the task to the next day when it can be performed cont...
eyalk2300
Sep 17, 2024Copper Contributor
Microsoft Project desktop
Sep 17, 2024
eyalk2300 --
You will need to edit the Standard calendar so that includes the holdiay you mentioned. Refer to the following YouTube videos on how to edit the Standard calendar:
https://youtu.be/GrR8v1Y4RN0
https://youtu.be/UOCuJdC9Oqc
Hope this helps.