Forum Discussion
James_Price
Jul 20, 2023Brass Contributor
Calendars in POL...
Hi team
In POL, I have replaced a project schedule in Project App, by copy and pasting in a local schedule and have imported the local calendar. However, I get an error when I try to publish. Does this mean that the calendar that I’ve imported has to be in the enterprise calendar?
I’m loathed to put in many calendars into the enterprise calendar as I’ve been told it takes up a lot of resource.
Any help gratefully received
Many thanks
James
- James --
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
2 Replies
- James --
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.- James_PriceBrass ContributorNice one Dale. Thanks again for your help.
James