Forum Discussion
James_Price
Jul 20, 2023Brass Contributor
Calendars in POL...
Hi team In POL, I have replaced a project schedule in Project App, by copy and pasting in a local schedule and have imported the local calendar. However, I get an error when I try to publish. Does...
- Jul 20, 2023James --
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
Jul 20, 2023
James --
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
James_Price
Jul 20, 2023Brass Contributor
Nice one Dale. Thanks again for your help.
James
James