Calendars in POL...
Hi team In POL, I have replaced a project schedule in Project App, by copy and pasting in a local schedule and have imported the local calendar. However, I get an error when I try to publish. Does...
- Jul 20, 2023James --
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
Jul 20, 2023
James --
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
The default functionality of Project Online requires that every project MUST have an enterprise calendar and not a local calendar. So, go ahead and put in as many calendars as you need into your Project Online system. Hope this helps.
- James_PriceJul 20, 2023Brass ContributorNice one Dale. Thanks again for your help.