Assigned Tasks not showing under "Tasks" and "timesheet" for team members

Hi Everyone, I have an issue I can't seam to solve, some of my team members cannot see their tasks under "Tasks" and "timesheet" even after the project has been published. I've looked at the info under their profile I can't see anything different with those who are able to access their tasks.

 

The administrator is however able to see task allocated to the team members but they cannot see under their personal profiles

 

Please help

 

Regards

Mpafane

  • Hello Mpafane,

    For these users, who is the default assignment owner? You can see this when you edit the resource in PWA. For existing projects, open a project in Microsoft project and insert the Assignment Owner column, does this match the assigned resource name or the name of the administrator user? If you want the users to see these tasks, make sure they are set at the assignment owners.

    Paul

3 Replies

  • Mpafane --

    In addition to Paul's excellent answer, you might want to display the Build Team dialog and to make sure that the Booking Type value is set to Committed for each of the resources in your project team. Hope this helps.
  • Hello Mpafane,

    For these users, who is the default assignment owner? You can see this when you edit the resource in PWA. For existing projects, open a project in Microsoft project and insert the Assignment Owner column, does this match the assigned resource name or the name of the administrator user? If you want the users to see these tasks, make sure they are set at the assignment owners.

    Paul

    • Mpafane's avatar
      Mpafane
      Copper Contributor
      Thanks a lot Paul Mather this has been very help full. Sorry for the late feedback I was on leave. Thanks once again