Hello Mpafane,
For these users, who is the default assignment owner? You can see this when you edit the resource in PWA. For existing projects, open a project in Microsoft project and insert the Assignment Owner column, does this match the assigned resource name or the name of the administrator user? If you want the users to see these tasks, make sure they are set at the assignment owners.
Paul
Hello Mpafane,
For these users, who is the default assignment owner? You can see this when you edit the resource in PWA. For existing projects, open a project in Microsoft project and insert the Assignment Owner column, does this match the assigned resource name or the name of the administrator user? If you want the users to see these tasks, make sure they are set at the assignment owners.