Assigned Tasks not showing under "Tasks" and "timesheet" for team members
Hi Everyone, I have an issue I can't seam to solve, some of my team members cannot see their tasks under "Tasks" and "timesheet" even after the project has been published. I've looked at the info und...
- Apr 19, 2021
Hello Mpafane,
For these users, who is the default assignment owner? You can see this when you edit the resource in PWA. For existing projects, open a project in Microsoft project and insert the Assignment Owner column, does this match the assigned resource name or the name of the administrator user? If you want the users to see these tasks, make sure they are set at the assignment owners.
Paul
Apr 19, 2021
Mpafane --
In addition to Paul's excellent answer, you might want to display the Build Team dialog and to make sure that the Booking Type value is set to Committed for each of the resources in your project team. Hope this helps.
In addition to Paul's excellent answer, you might want to display the Build Team dialog and to make sure that the Booking Type value is set to Committed for each of the resources in your project team. Hope this helps.