parlisingh
Aug 17, 2022Copper Contributor
% Work Complete Status
A have a project plan and had about 300 lines as was progressing through project the % Work complete was showing as 20%. I have added a further 200 lines, and increased the length of the project. The % work complete still shows 20%. I can manually mark items as complete and that increases % complete. however adding more tasks or significantly increasing the amount of time on a task(s) doesn't change the % work complete field.
Problem: Because we have only started project, i would say we are only about 5% into the project (No of hours billed versus forecasted hours) but project is showing as 20% complete. Why is this?
- parlisingn,
Duration doesn't necessarily "map" back to actual work. For your server example, it sounds like you should use fixed duration as your task type. Duration is entered as a week. The 3 hours of labor (work) to accomplish that task may be linearly spread over the week, occur all on the first day, all on the last day or any combination thereof.
John