Forum Discussion
% Work Complete Status
- Aug 31, 2022parlisingn,
Duration doesn't necessarily "map" back to actual work. For your server example, it sounds like you should use fixed duration as your task type. Duration is entered as a week. The 3 hours of labor (work) to accomplish that task may be linearly spread over the week, occur all on the first day, all on the last day or any combination thereof.
John
My guess is that you have not selected the option to tie % Complete to % Work Complete (i.e. task status versus resource status). This option is set under, File > Options > Schedule Group > Calculations for project > "Updating Task status updates resource status".
I assume you are referring to the % Complete value shown for the Project Summary Task. The % Complete value for any summary line is calculated by Project as:
% Complete = (Sum of all subtask actual durations)/(sum of all subtask durations) * 100%
When you add tasks, you are increasing the sum in the denominator of the equation.
Hope this helps.
John
- parlisinghAug 18, 2022Copper Contributor
- John-projectAug 18, 2022Silver Contributor
Thanks for the screen shot, it doesn't tell me everything but it does give some critical information.
First, I note you have successor links on some summary lines. Summary lines are not tasks and should neither have links (predecessor/successor) nor resources assigned. I suggest you re-structure your plan to address that issue. The risk you run for not doing so is even more things that don't make sense.
Percent Work Complete is calculated by Project as, Actual Work / Work * 100%. Simply adding tasks to your plan will not change the % work complete value until actual work is accrued. If you manually edit tasks as complete via the % Work Complete field, because the option to link task status with resource status is checked, that will then also update the % Work Complete field.
When you say % Work Complete doesn't change even though you "significantly increase the amount of time", are you talking about increasing the task duration or the amount of work? I suspect you are referring to increasing the duration. Also, are there resource assigned to the tasks where you "increased the amount of time"?
When you say you are only about 5% into the project (billed versus forecasted) how does that relate to how the plan was updated (i.e. what was entered for work and actual work)? The 20% shown by Project is calculated based on that data, not on how much was billed.
John
- parlisinghAug 18, 2022Copper ContributorWhen you say % Work Complete doesn't change even though you "significantly increase the amount of time", are you talking about increasing the task duration or the amount of work?
- Task Duration
I suspect you are referring to increasing the duration.
Also, are there resource assigned to the tasks where you "increased the amount of time"?
- yes
When you say you are only about 5% into the project (billed versus forecasted) how does that relate to how the plan was updated (i.e. what was entered for work and actual work)? The 20% shown by Project is calculated based on that data, not on how much was billed.
- The actual hours vs forecasted hours was done by spreadsheet. Not in project. Plus from a PM perspective, (understanding where a project is) it doesnt feel right we are 20% done. More like 5-10% but that is subjective (e.g. we havent even gotten the trequirements documented), all the current work done is just prep and plannng.