Forum Discussion

parlisingh's avatar
parlisingh
Copper Contributor
Aug 17, 2022
Solved

% Work Complete Status

A have a project plan and had about 300 lines as was progressing through project the % Work complete was showing as 20%.  I have added a further 200 lines, and increased the length of the project.  T...
  • John-project's avatar
    John-project
    Aug 31, 2022
    parlisingn,
    Duration doesn't necessarily "map" back to actual work. For your server example, it sounds like you should use fixed duration as your task type. Duration is entered as a week. The 3 hours of labor (work) to accomplish that task may be linearly spread over the week, occur all on the first day, all on the last day or any combination thereof.

    John

Resources