% Complete in Planner Graph API?
I've been exploring the Planner Graph API and Planner Flow Connector for some integration work we have planned. There is a "percentComplete" attribute exposed via both connections. How is the value o...
- Jan 03, 2019
The '% Complete' field is set by changing the Progress field.
- Not started = 0%
- In progress = 50%
- Completed = 100%
Eric Eaton
Jan 03, 2019Iron Contributor
The '% Complete' field is set by changing the Progress field.
- Not started = 0%
- In progress = 50%
- Completed = 100%