Project days in each quarter

Hi am looking for a solution
I have A1= Start Date, B1= End Date , C1=Q1'20,D1-Q2'20,E1Q3-20,F1-Q4'20, G1= Q1'21,......N1=Q4'22.all up to 12 quarters.
i need a solution- 
the number of project days falling in each of the quarter with my upper limit and lower limit of dates is 1-Jan-20 and 31-Dec-22, A1 and B1 dates could be any days, am only looking how many days in each quarter the project is active between 1-Jan-20 and 31-Dec-22 and they should be in each quarter

5 Replies

      • Abhyudoy's avatar
        Abhyudoy
        Copper Contributor
        HansVogelaar

        Thank you for your quick response, in your solution its returning 93 days between start date and end date, however it should be 92 days...i tried to correct ,,but not finding..:-(..can you help