Forum Discussion
Abhyudoy
Nov 24, 2021Copper Contributor
Project days in each quarter
Hi am looking for a solution I have A1= Start Date, B1= End Date , C1=Q1'20,D1-Q2'20,E1Q3-20,F1-Q4'20, G1= Q1'21,......N1=Q4'22.all up to 12 quarters. i need a solution- the number of project day...
Abhyudoy
Nov 24, 2021Copper Contributor
Abhyudoy
Nov 24, 2021Copper Contributor
HansVogelaar
Thank you for your quick response, in your solution its returning 93 days between start date and end date, however it should be 92 days...i tried to correct ,,but not finding..:-(..can you help
Thank you for your quick response, in your solution its returning 93 days between start date and end date, however it should be 92 days...i tried to correct ,,but not finding..:-(..can you help
- AbhyudoyNov 24, 2021Copper ContributorHansVogelaar
Thank you so much for you help!! - HansVogelaarNov 24, 2021MVP
Simplified example:
Start Date = November 19, 2021
End Date = November 22, 2021
The difference is 22-19 = 3 days, but the time interval contains 4 days: November 19, 20, 21 and 22.