Forum Discussion
Please help me fill due date column.
- Nov 01, 2020
Since you are looking for a dynamic method, therefore I would like to suggest below shown method to be followed.
How it works:
- Press Ctrl+F3 to get Range Name dialogue.
2. Enter an appropriate name in Name box.
3. Use this formula for references.
=OFFSET(Sheet2!$J$25, 0, 0, COUNTA(Sheet2!$J:$J), 1)Note:
- Purpose of doing this, if in future you need to add more Task along with days to add then no need to modify the cell references in the formula.
- Repeat step 1 to 3 for "Days to add column", and use this formula.
=OFFSET(Sheet2!$K$25, 0, 0, COUNTA(Sheet2!$K:$K), 1) Note: Name given to cloumn is ValueList.- Now enter this formula in cell I25 and fill down.
=IF(ISBLANK(G25),"",H25+VLOOKUP(G25,CHOOSE({1,2}, TaskList, ValueList),2,FALSE))Adjust cell references in the formula along with Task List & related Days to add, as needed.
**** If this works for you then, you may mark it as best answer as well Like.
Riny_van_Eekelen Thank you so much. I am new to excel and would love to as much as I can. I appreciate your help. Thanks a lot.
Can I create a Dashboard for analysis in excel?
JayJoshi You're welcome!
Excel is capable of doing many things, including dashboards. Though, that is not something I specialise in. I suggest you come back here with a new question, once you are able to explain what kind of summary/analysis/reports/graphs you want to create on whatever data you are working with.
- JayJoshiOct 31, 2020Copper Contributor
Riny_van_Eekelen That makes sense. Thank you so much for that. I will post a new question for that.