Planned maintenance scheduler
Hi All, So I'm making a maintenance scheduler and its start up and some dates completed dates I don't know yet but I have frequency so ive put a formula of completed dates plus date frequency = n...
- Dec 15, 2023
Use this as formula for the Due column:
=IF([@Completed]="", "", [@Completed]+[@[Frequency (Days)]])
HansVogelaar
Dec 15, 2023MVP
Use this as formula for the Due column:
=IF([@Completed]="", "", [@Completed]+[@[Frequency (Days)]])
- AhmetHaDec 15, 2023Copper Contributorworks perfectly thank you very much