Graph Overlay Weekly Progress
Hi all,
Looking for tutorial or advice.
I'm looking for a way to capture weekly data (%) progress and make it static (snapshot), then overlay this over the next weeks' progress.
This is so I can show the progress from the previous weeks work. I.E. actively showing that I am progressing from the previous weeks work. Then I can describe callouts/dependencies/blockers to justify why/if I haven't progressed from last weeks position.
I've found a lot of material on just showing progress, but not on overlaying it against a previous weeks goals.
If that makes sense?
Regards,
N
1 Reply
Sort By
- Riny_van_EekelenPlatinum Contributor
What makes sense and what not depends on who you ask! It could be as simple as a line chart showing cumulative progress against cumulative goal, as shown in the picture below. Horizontal on the blue line means "no progress" compared with the previous week.