I have a Gantt chart in Excel to help us with project management and timing. I found an example a few weeks ago and have modified it to get about 95% of the way done. The issue is weekends. The char...
- Nov 15, 2024
In columns H and I, change formulas such as
=I9-D9
to
=WORKDAY(I9, -D9)
HansVogelaar
Nov 15, 2024MVP
In columns H and I, change formulas such as
=I9-D9
to
=WORKDAY(I9, -D9)
MichelBryson
Nov 15, 2024Copper Contributor
Thank you so much HansVogelaar ! I'm going to build a template for my team, working back from launch dates. Then I also hope to make one for working forward from a start date as well.
You've been an incredible help, and I cannot even begin to express how much I appreciate your assistance!