Gantt Chart without weekends

I have a Gantt chart in Excel to help us with project management and timing. I found an example a few weeks ago and have modified it to get about 95% of the way done. The issue is weekends. The char...
  • HansVogelaar's avatar
    HansVogelaar
    Nov 15, 2024

    In columns H and I, change formulas such as

    =I9-D9

    to

    =WORKDAY(I9, -D9)