Hello, I am working on a project and using excel to forecast and track milestones. I am looking for a formula that will add 7 days to another cell, unless another cell has a date, then add 7 days to ...
- Feb 07, 2020Assuming your first row of data begins in cell A4, the task 2 forecast formula in column C4 could be:
=IF($B4>””, $B4+7, $A4+7)
Charla74
Feb 07, 2020Iron Contributor
Assuming your first row of data begins in cell A4, the task 2 forecast formula in column C4 could be:
=IF($B4>””, $B4+7, $A4+7)
=IF($B4>””, $B4+7, $A4+7)
archer2020
Feb 07, 2020Copper Contributor
Charla74 One problem I have with this formula is that when I drag the formula down the column it changes to 1/7/1900 if there is no date in B4...
- Charla74Feb 08, 2020Iron ContributorTry this one where we now check that A4 is not blank before calculating - if A4 is blank it should now return a blank result:
=IF($B4>””, $B4+7, IF($A4>””, $A4+7, “”))