Forum Discussion

Mya_10's avatar
Mya_10
Copper Contributor
Aug 22, 2023
Solved

Duration Dependency

Is there a way to keep a duration even if a start or end date changes?    For example: I have a task that needs to be completed in 5 days. The initial start date was 8/20 and the end date was 8/24....
  • leoperdia's avatar
    Aug 23, 2023

    Hi Mya_10 I'm not sure If I got you clearly but I suppose below model could be a solution:

     

    Introducing the concept of Forecast and Real. 

     

    Regards

    Leonardo

    https://www.upwork.com/freelancers/~01cf0fc8446b00f44c 

     

     

Resources