Forum Discussion
LC34VAN
Jan 10, 2021Copper Contributor
Calculating business days
Hi, I am new to excel but need to calculate business days excluding weekends and bank holidays from time received rather than the full start and end date. I.e if the start time is 28-03-2019 15:30 it will finish on 29-03-2019 15:29. Any assistance would be much appreciated. Thanks
6 Replies
- Riny_van_EekelenPlatinum Contributor
LC34VAN You may look into functions NETWORKDAYS and/or NETWORKDAYS.INTL
- LC34VANCopper Contributor
Riny_van_Eekelen Thanks I have tried those but they return 2 full days. I need to be able to start the day part way through and then calculate 24 hours from that time to the next business day so it’s calculated as 1 day rather than 2.
- SergeiBaklanDiamond Contributor