Project
735 TopicsProject Remaining Duration as of Status Date
In a Project schedule, The % Complete entered during an update doesn't seem to push the task Finish Date as it should. The task has a Start date of 6/9/25, Finish date of 9/23/25, duration of 14.95 weeks. The Status date is 9/12/25, Actual start 6/9/25 (on schedule) but progress is 2% Complete, Remaining Duration is 13.45 wks. When I click Update Project and reschedule uncomplete work to start as of Status Date (9/12/25) the Finish Date remains 9/23/25. Shouldn't the Finish Date push to approx. 12/12/2025 based on the % complete and remaining duration? There are no date constraints on the task, and "Split In-Progress tasks" is selected in the Schedule Options. There are a handful of tasks in this schedule with a similar issue.76Views0likes6CommentsCreating a Project through Graph API "msdyn_CreateProjectV1"
I want to create a new Project online plan using Microsoft Graph API, so i used this end point and action inside my flow:- now the action will run successfully, and it should have created a new Project with subject = "Subject Test from automate", as follow:- but i can not find the new project inside the UI:- any advice?64Views0likes1CommentCannot Force Checkin: Project Web App
My team got project stuck in the queue and we can't publish any other projects as 2 jobs got stuck and causing other projects to continue to be in a wait. I tried to 1) Cancel the publish job (not successful) force checkin a project (not successful either) and it continues to stay in this state for several hours "Waiting To Be Processed" Please help!!1.2KViews0likes2CommentsProject online REST API for Project Manager approval on Task status update
Hi all, I am currently working on a custom solution that integrates multiple functionalities interacting with Project Online data. As part of a new requirement, whenever a team member submits a task update in timesheet, I aim to provide Project Managers with the ability to approve task updates directly from a custom page. My initial approach was to utilize the Project REST API (_api/ProjectServer), but I have not been able to locate an appropriate endpoint that supports this functionality. Could anyone kindly guide me to the specific REST API endpoint (if available) that can be used to approve task updates? Any insights or alternative approaches would be greatly appreciated. Thanks in advance. Regards Shruti Vyas122Views0likes1CommentOpening and Viewing Option for Two MS Project Files Simultaneously on Two Screens?
Hi Can two MS Project files be opened on two different screens at the same time? This option is should be there as it is for other usual MS software like Word, Excel etc. Hope this can be fixed as will ease out while working from two parallel files simultaneously. Appreciate if this can be looked at, please asap. Looking forwardSolved155KViews1like41Comments"Insufficient privileges to complete the operation" when listing Planner tasks from Project
Hi, it's only my time posting here, please let me know if I should be doing something differently! I've searched throughout the internet and couldn't find a solution for this. I've got a user running into a problem where the `/me/planner/tasks`, `/planner/buckets/{bucketId}/tasks`, and `/planner/plans/{planId}/tasks` endpoints return a `Authorization_RequestDenied` error. Here's an example response: { "code": "Authorization_RequestDenied", "message": "Insufficient privileges to complete the operation.", "innerError": { "date": "2025-07-23T08:15:50", "request-id": "bd5f7056-a41d-439c-a0d7-d768cd82d1ea", "client-request-id": "362f376c-863e-0616-86f7-22c7c07c1352" } } While this happens for almost all of their groups and plans, it doesn't happen for one. The main difference between that which works and the other ones which don't is that all the ones that don't work were created in Microsoft Project (Platinum, I think?). The one that does was created in Planner. We can, however, list the proper plans and buckets, just not fetch the tasks. Is there any way around this? Is there some kind of special scope I should be asking for so the API calls work? Should I use the To Do API in some special way for this, instead? Thank you so much!52Views0likes0CommentsRow height issue
Hello, I have been facing recently issue with automatic row adjustment (Microsoft® Project 2016 MSO (Version 2505 Build 16.0.18827.20102) 64-bit): anytime I make any change on any of the rows, Project automatically changes the heigh of some of the rows into random height. Selecting/unselecting Wrap Text does not help - when clicking the Wrap text, the rows are readjusted to single line, but when I make another change in Gant (eg update % Completion), the rows height changes again. So basically after every change in gant, I need to select or unselect Wrap Text (the same result ) to get back single line per row view. I went throught the forum and tried advices: Bar Styles - check all on row 1, Bar Styles - bars without text, Bars/Layout - decrease the bar heigh. Nothing helped so far. Can anobody help, or is it a SW bug?Solved174Views0likes6CommentsIntegrating ESS Utumishi with Microsoft 365 and SharePoint: Best Practices and Insights
I’m working on a project to integrate ESS Utumishi, the Tanzanian government’s Employee Self-Service platform, with modern content management solutions like Microsoft 365 and SharePoint. My goal is to improve document management, automate HR workflows, and enhance overall employee engagement through a seamless digital experience. Has anyone worked on similar integrations or faced challenges in connecting government HR systems with Microsoft tools like in essutumishigotz.com? I’d love to hear about any best practices, lessons learned, or success stories that could help guide this project, especially in terms of improving system efficiency and user adoption in the public sector.32Views0likes0Comments