Forum Discussion

FilipeCuango's avatar
FilipeCuango
Copper Contributor
Mar 31, 2022

Tasks with different calendar times

Hello Team. I'm stuck in a following situation. I have a 4 hour schedule (09:00 – 13:00) with a 20 minute break. Along the schedule I have special activities that must start at 10:00 to finish at ...
  • John-project's avatar
    John-project
    Apr 01, 2022

    FilipeCuango 

    That's because you've given Activity 2 a duration of 1 day which is 3.67 hours and if Activity 2 starts one hour later than the normal start time of 9:00 AM, that 1 day duration will push Activity 2 into the second day.

     

    I would not create a separate calendar for the special tasks that start one hour later. If those special activities are indeed dependent on other tasks (i.e. Finish-to-start relationship) put a lag in the Predecessor (i.e. Activity 1 + 1h).

     

    As I noted, for the type of scheduling you are doing I would avoid entering task duration in days or even hours since rounding will cause problems with the display. I'd enter all durations in minutes. That will give the cleanest and most accurate presentation.

    John