schedule
1 TopicTasks with different calendar times
Hello Team. I'm stuck in a following situation. I have a 4 hour schedule (09:00 – 13:00) with a 20 minute break. Along the schedule I have special activities that must start at 10:00 to finish at 13:00. This is where the headache starts. I can't help it, I've already tried adding lag, creating a new calendar to add to these special tasks and adding slack. Unfortunately, every attempt led me to an activity that always ended the next day, outside the intended range. As I intend, a one-day activity that starts from 10:00 to 13:00, although my project calendar is set to 09:00 – 13:00 as in the schedule optionsSolved1.5KViews0likes5Comments