Forum Discussion
Task with choise between 2 (or more) resources
In my project I have 2 resources, I'll call them A and B. Some task can only be performed by resource A, but other task can be done by either A or B, but never A and B together.
I tried to solve this by assigning both A and B to the tasks that either of them can do and put them at 50%. This way 2 tasks can be performed concurrently. However if resource A is working on a task which only A can perform, B is also idle because A is 100% occupied.
Is there a way to tell a task to use "Resource A" or "Recource B"? Or another work around?
To make my question more concrete. Resource A and B in my project are cranes that have to lift certain loads. Crane A is bigger than crane B, so some loads can only be lifted by crane A and some can be lifted by crane B or A, whichever happens te be available.
__PRESENT
Unless one of my colleagues can suggest a clever solution, I'd say the answer is "no". Project just doesn't have the capability of making either-or decisions. It could be done with an algorithm and a macro but nothing that exists directly in the app itself will make the crane assignment decision for you.
Sorry, but hope it helps.
John
- John-projectSilver Contributor
Unless one of my colleagues can suggest a clever solution, I'd say the answer is "no". Project just doesn't have the capability of making either-or decisions. It could be done with an algorithm and a macro but nothing that exists directly in the app itself will make the crane assignment decision for you.
Sorry, but hope it helps.
John