Task with choise between 2 (or more) resources

In my project I have 2 resources, I'll call them A and B. Some task can only be performed by resource A, but other task can be done by either A or B, but never A and B together.  I tried to solve th...
  • John-project's avatar
    Oct 14, 2024

    BoonsBruno 

    Unless one of my colleagues can suggest a clever solution, I'd say the answer is "no". Project just doesn't have the capability of making either-or decisions. It could be done with an algorithm and a macro but nothing that exists directly in the app itself will make the crane assignment decision for you.

     

    Sorry, but hope it helps.

    John