Sorting tasks chronologically including summary tasks/sub projects

Copper Contributor

Hello, 

 

I need to sort the tasks of a project plan which includes sub projects. 

If I simply sort the task dates chronologically, the result is, that it only sorts the start and end date of each sub project. What I need to do though is to sort all tasks of these sub projects, regardless of which sub project they come from. 

 

Any ideas? 

3 Replies
best response confirmed by Dale Howard (MVP)
Solution
mamuench,
Go to, View > data group > Sort. When the Sort window appears select "sort by". Uncheck the option to "Keep outline structure". Then select the Start field as the 1st criteria.

Hope this helps.
John
mamuench,
You're welcome and thanks for the feedback.
John
1 best response

Accepted Solutions
best response confirmed by Dale Howard (MVP)
Solution
mamuench,
Go to, View > data group > Sort. When the Sort window appears select "sort by". Uncheck the option to "Keep outline structure". Then select the Start field as the 1st criteria.

Hope this helps.
John