Sorting tasks chronologically including summary tasks/sub projects

Hello,    I need to sort the tasks of a project plan which includes sub projects.  If I simply sort the task dates chronologically, the result is, that it only sorts the start and end date of each...
  • John-project's avatar
    Feb 28, 2024
    mamuench,
    Go to, View > data group > Sort. When the Sort window appears select "sort by". Uncheck the option to "Keep outline structure". Then select the Start field as the 1st criteria.

    Hope this helps.