Forum Discussion
mamuench
Feb 28, 2024Copper Contributor
Sorting tasks chronologically including summary tasks/sub projects
Hello, I need to sort the tasks of a project plan which includes sub projects. If I simply sort the task dates chronologically, the result is, that it only sorts the start and end date of each...
- Feb 28, 2024mamuench,
Go to, View > data group > Sort. When the Sort window appears select "sort by". Uncheck the option to "Keep outline structure". Then select the Start field as the 1st criteria.
Hope this helps.
John
mamuench
Feb 28, 2024Copper Contributor
John-project Yes, thank you very much!
John-project
Feb 28, 2024Silver Contributor
mamuench,
You're welcome and thanks for the feedback.
John
You're welcome and thanks for the feedback.
John