Forum Discussion

Ollie's avatar
Ollie
Brass Contributor
Feb 07, 2024
Solved

Project for the web - Recycle bin / Versioning

Hi, 

 

Is there any facility in Project for the Web to track changes to a project or recover deleted items? 

 

Ollie

  • Oliver --

    There is no Recycle Bin for Project for the Web. The tool DOES offer a Task History feature, but this is only for individual tasks. Hope this helps.

3 Replies

  • JeanParcks's avatar
    JeanParcks
    Copper Contributor
    Does Project for the web offer any features for tracking changes made to a project or restoring deleted items? I am interested in the possibilities of the platform in this regard. If you are interested in web projects, you can always contact saas website design agency https://fivecube.agency/services/saas-website-design-agency for help.
  • RodFromm's avatar
    RodFromm
    Iron Contributor
    In addition to what Dale posted, Microsoft currently does not provide any backup/restore functionality for projects in the default environment. Named instances are backed up, but when you restore it, it is restored to a new separate instance. I believe there are third party vendors that provide more robust backup and restore functionality.
  • Oliver --

    There is no Recycle Bin for Project for the Web. The tool DOES offer a Task History feature, but this is only for individual tasks. Hope this helps.

Resources